Main wheel clicks; begin escapement antifriction wheel assembly, August 2008

Back Up Next

Below photos show most of the parts fabricated for the main wheel click springs. There are four identical sets for the four trains (eight clicks). Clicks will be arranged so each pair of clicks will engage the ratchet wheel in 1/2 tooth increments. This will give twice the number of audible clicks for each revolution of the ratchet wheel. It's the same system used for tall fly fan assemblies. Parts count for this system 52.

Astro 08-08 (2).jpg (155329 bytes) Astro 08-08 (1).jpg (160495 bytes) Astro 08-08.jpg (130067 bytes)

First photo showing proposed positions for the click spring feet. The frame outline is made from paper and pasted to the clear plastic frame to test where the feet can be placed thus determining the length of the click spring. Following photos begin the fabrication of the escapement system. It's interesting to note that in most conventional clock designs the escapement would be composed of maybe one or two dozen parts; the escape wheel, the escapement pallet, crutch and pendulum. In this project the parts count for the same components will be close to 700.

Astro 08-08 (3).jpg (159779 bytes) Astro 08-08 (4).jpg (141581 bytes) Astro 08-08 (5).jpg (151543 bytes)

Numerous screws, all custom made. Next a shot of an initial antifriction wheel assembly.

Astro 08-08 (6).jpg (143705 bytes) Astro 08-08 (10).jpg (157755 bytes)

The eight support plates for the eight antifriction wheels that will compose the escapement support and drive system. Each antifriction wheel will run in jeweled chatons.

Astro 08-08 (8).jpg (144622 bytes) Astro 08-08 (9).jpg (149806 bytes)

Antifriction wheels in the rough showing their positions. Next the fabrication of the bevel wheels that will drive the escapements.

Astro 08-08 (7).jpg (152795 bytes) Astro 08-08 (11).jpg (152733 bytes)

Further shots of the escapement bevel drive wheel fabrication.

Astro 08-08 (12).jpg (138203 bytes) Astro 08-08 (13).jpg (155261 bytes)

The design of this wheel is special. There is an additional inner ring that will be used as a thrust bearing acting upon an antifriction wheel to prevent the wheel from moving outward as is the case on any bevel wheel arrangement. Next two photos show progress in the bevel as well as antifriction wheel fabrication.

 Astro 08-08 (14).jpg (162429 bytes) Astro 08-08 (15).jpg (146437 bytes)

The drawing is a a proposal of two designs that was submitted for the antifriction wheel cocks. I chose the first, 'A'.

Astro 08-08 (16).jpg (147181 bytes) Astro 08-08 (17).jpg (629026 bytes)

During this time the going train was able to be put to a weight to see approximately what the power input would be needed to run the clock. The first serious design setback was now encountered. The fabricator had miscalculated the weight-to-duration needed to drive the clock by 100%. So the going (time) train which had been estimated to run for 8 days on a weight of 70kg (154 lb.) falling 3 1/2 feet will, at best, get 4 days. This is a major setback. But, in my opinion, not totally unexpected. This design has a huge number of mobiles, and is a large scale so there is a large amount of mass to be moved. Three feet on an eight day duration is a tough condition for even a conventional design let alone for this one. We will address this duration issue as the clock is made, but for now the going train will be four days with the remaining trains being 8 days - so far. This test is shown below.

                                                      

                                                                                   Loop:

                                                              Astro_08-08_vid.mpg   Astro_08-08_vid_2.mpg  Astro_08-08_vid_3.mpg

Back Up Next